General Description:
The CUBE Battery System consists of air-cooled battery modules utilizing Lithium Ferrophosphate battery cells (LFP). The battery system is scalable to up to sixteen battery strings, containing from one up to eleven battery modules, to reach the required total battery capacity and/or system voltage. A Switch Unit including the master battery management system is part of the system. A battery string consists of a Switch Unit and up to eleven battery modules.
CUBE Battery Module:
Energy 12,5 kWh
Capacity 163 Ah
Configuration 1P24S
Cooling Air cooled
Nominal voltage 77 V
Max. voltage (100% SoC) 87 V
Min. voltage (0% SoC) 60 V
Max. charge current 163 A
Max. discharge current 163 A
Max. discharge peak current (10s) 200 A
Weight 96 kg
Protection class IP65
Switch Unit
Max. voltage 1000 V
Max. current 250 A
Fuse 125 A
Precharge resistor 100 Ohm
Weight 20 kg
Protection class IP66
Control Cabinet
Power supply: 24 V DC
Power consumption: 88 - 730 W (1 Rack - 16 Racks)
Connected racks: up to 16
Degree of protection: IP66
TYPE APPROVAL CERTIFICATE
No. ELE074624XG
Enclosure - Page 2 of 4
CUBE Software:
CobraSense42 Slave Software V2.xx
CobraSense42 Master Software V2.xx
PLC Software V2.xx
BMS Master Software V2.xx
Hardware
Control Cabinet CC1Dxxxxxxx
Switch Unit SU1Gxxxxxxx
Battery CUBE BC0Bxxxxxxx
CobraSense42 Slave V3.01
CobraSense42 Master V2.02
String
Cube Count | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | Unit |
| Nominal Voltage | 77 | 154 | 231 | 308 | 385 | 462 | 539 | 616 | 693 | 770 | 847 | V |
| Max. voltage (100% SoC) | 87 | 174 | 261 | 348 | 435 | 522 | 609 | 696 | 783 | 870 | 957 | V |
| Min. voltage (0% SoC) | 60 | 120 | 180 | 240 | 300 | 360 | 420 | 480 | 540 | 600 | 660 | V |
Battery Cube (BC)
The Battery CUBE contains 24 single accumulator cells and two CMUs plus the CobraSense42 Slave. The BMS slaves basic function is the measurement of cell voltages and temperatures. The basic function of the CobraSense42 Slave is to host independent safety functions, like redundant temperature detect on and gas detection.
Battery Management System (BMS) and system overview
The BMS and independent safety system consits of BMS Master, BMS Slave (Cell monitoring), COBRASense42 Master and COBRASense42 Slave.
BMS Cell Monitoring Unit (CMU)
The slave-BMS consists of two single boards. Those are located in the battery modules. Their purpose
is to measure the status of the LFP cells and transmit the data to the master BMS. Each slave board can measure the voltage of up to twelve cells.
COBRASense42 Master (CS42M)
This unit is installed in the switch box. It communicates with the COBRASense42 Slave and monitors
the pilot line. Additionally, it controls the module heating.
TYPE APPROVAL CERTIFICATE
No. ELE074624XG
Enclosure - Page 3 of 4
CUBE
COBRASense42 Slave (CS42S)
This unit is part of the battery module and is designed for independent safety functionality. The function of the board is to detect cell venting, redundant temperature monitoring. A safety line trips the main breaker in case of detected fault.
Switch Unit (SU)
The unit comprises the BMS Master, COBRASense42 Master, two power fuses and two circuit breakers.
BMS Master Control Unit (MCU)
It creates the interface between BMS and PLC.
Control Cabinet (CC)
Each battery system (comprising of 1 to 16 battery strings) is connected to one control cabinet, which manages the basic system functions and the the interface to the ship's automation system.
Remarks:
- Each particular application and installation such as electric propulsion and essential services, or for the charging/discharging of battery systems of a capacity of 50 kWh or above are to be specifically approved and the following documents are to be submitted for approval:
1. Reference to this type approval certificate
2. safety description
3. Project-specific Battery System Block Diagram
4. Technical specification of the battery system that is subject for product certification
5. Electric schematic diagram of the battery system showing internal arrangement of battery modules, battery strings, switch unit, emergency stop and independent safety system
6. Functional description, including a project-specific overall description of the battery management system software and hardware versions of components
7. Capacity calculations for the gas extract ventilation fan other relevant information not covered by the safety description
8. Test program for product certification, including routine tests specified in applicable rules
9. Calculation report, documentation of the SOC and SOH calculation
- Factory Acceptance Test - FAT is to be carried out on the battery system (BMS and Battery Cells) for each project according to RINA Rules Pt C, Ch 2, App 2 par. 5.2
- Testing and inspection after installation on board are to be performed for each project according to RINA Rules Pt C, Ch 2, App 2 par. 5.3
- The battery system is to be used in connection with an appropriate PMS able to shut down the battery pack in case of an identified failure.
- Installation of the battery system is to be in accordance with RINA Rules Pt C, Ch 2, App 2 and manufacturer´s instruction taking into account the defined environmental conditions.
- The battery system is not to be installed on the navigation bridge, open deck or hazardous zone.
- This Type Approval Certificate does not cover any Flag Administration requirements.
TYPE APPROVAL CERTIFICATE
No. ELE074624XG
Enclosure - Page 4 of 4
CUBE
Documents:
CUBE System Description Rev 01
CUBE Functional Description Rev 01
CUBE Specification Rev 03
CUBE Operating and Maintenance Manual Rev 05
CUBE Installation Manual Rev 03;
CUBE Safety Description Class Rev 02
CUBE Calculations Rev 01
CUBE List of Versions Rev 03
CUBE Single Line System Rev 03
CUBE Circuit Diagram Control Cabinet CC0D Rev 01
CUBE Circuit Diagram Battery Module BC0B Rev 01
CUBE Circuit Diagram Switch Unit SU1G Rev 02
CobraEMC V1.0A Circuit Diagram 1.0A
CobraSense42M V2.02-B Circuit Diagram 2.02-B
CobraSense42S V3.01-F Circuit Diagram 3.01-F
CUBE External Datasheets Class Rev 01
Test Reports:
CUBE External Datasheets Class Rev 01 IEC62619 - Cell test 7.2.1, 7.2.2, 7.2.4, 7.2.6
2024-05-28 CUBE BC0B IEC62619_7.2.3.3 Protocol BU-202400129-B1
2024-06-14 CUBE BC0B IEC62619_7.3.3 Protocol
2024-06-20 CUBE BC0B IEC62619_8.2.2 Protocol
2024-06-21 CUBE BC0B IEC62619_8.2.3 Protocol
2024-06-27 CUBE BC0B IEC62619_8.2.4 Protocol
2023-07-30 IEC62620_6.3.1_6.3.2_6.3.3_6.4_6.5.2_6.5.3 Protocol BU-202300263-B1
2024-06-13 CUBE BC0B IEC62620_6.3.1_6.3.2_6.3.3_6.5 Protocol BU-202400088-B1
2023-05-03 IEC62620_6.6.1 Protocol
2024-06-26 Gas Analysis Protocol Rev 02
2024-05-27 CUBE BC0B UN38.3_T1_T2_T3_T4_T5 Protocol BU-202400087-B1
2024-08-26 CUBE BC0B IACS_E10_EMC Protocol TREO-280-24_V1U
2024-08-26 CUBE BC0B IACS_E10_ENV Protocol TREO-206-24_V2U
2024-06-14 CUBE BC0B Functional Tests Class Protocol Rev 02
2024-08-27 CUBE BC0B Functional Tests Class Protocol Rev 02-b |
|